MYNYDD CLOGAU WIND FARM, POWYS, MID-WALES

  • Capacity 15MW
  • Commissioned in January 2006
  • 17 turbines (0.85MW Vestas)
  • 5 separate land owners


LISSETT AIRFIELD WIND FARM, EAST RIDING OF YORKSHIRE

  • Capacity 30MW
  • First production in February 2009
  • 12 turbines (2MW N90 Nordex)
  • 1 land owner
More on Lissett Airfield >>

LOCAL COMMUNITY SUPPORT

The Community Funding Scheme that Novera runs at Mynydd Clogau has led to improvements to local roads and the establishment of two Trust Funds to ensure that some of the revenue generated by the wind farm directly benefits the local Community.

Novera has submitted a planning application for a wind farm (Mynydd Clogau 2) alongside Mynydd Clogau view more.

SLIDESHOWS
Slideshow image
Operations
 
 
Click for more on Landfill Gas
Landfill Gas
(LFG) provides 29 per cent of the UK’s renewable power. view more
 
Click for more on Hydro Power
Hydro Power
A well established renewable energy power source. view more
 
Click for more on Wind Power
Wind Power
Novera’s strategic focus is on developing onshore wind projects. view more
 
Contact Us
Contact Us
Novera Energy location details and contact information click here
 
Sitemap
© Novera Energy 2010 | Designed & Built by BBDesign |